ap

Skip to content
Denver Post reporter Mark Jaffe on Tuesday, September 27,  2011. Cyrus McCrimmon, The Denver Post
PUBLISHED:
Getting your player ready...

Xcel Energy and a band of opponents are set to square-off Wednesday over whether the utility gets the final $16.6 million in cost overruns for the its SmartGridCity project.

Opponents of Xcel’s request to the Colorado Public Utilities Commission to include the costs in customer rates include the City of Boulder, the Climax Molybdenum Mine Co. and the state Consumer Counsel.

The SmartGridCity pilot in Boulder was one of the first and most comprehensive experiments in the nation with smart-grid technology, which uses computers to manage electricity distribution.

It was launched in 2008 with a price tag for Xcel of $15.3 million but

The total cost of the project — which connected 23,000 homes in Boulder with smart meters — is estimated at $100 million.

Sharing the cost were six high-tech companies partnering in the project, Xcel said.

In January 2011, the utility commission allowed Xcel to include $27.9 million in the rates of all Xcel customers, but withheld the last $16.6 million until Xcel could show that the pilot benefitted all Colorado ratepayers.

In filings to the commission, executives at Xcel’s subsidiary Public Service Company of Colorado said that the benefits included:

• A better management of voltage that saved $66,216 in fuel and, if used systemwide, would save $28 million in fuel a year.

• Being able to remotely diagnose and solve some problems at the 23,000 homes with smart meters in Boulder.

“This was a first-of-its-kind project and we incurred unexpected costs,” Michael Lamb, an Xcel executive, said in a filing.

Those contentions are being challenged in a spate of filings.

“Public Service made a lot of promises early on about what SGC would be and what it would do,” said Frank Schafer, a financial analyst with the consumer counsel. “Many of those promises have still not been realized.”

Kelly Crandall, a sustainability specialist for the City of Boulder, in testimony said SmartGridCity was plagued by ” poor planning and lack of comprehensive vision.”

Climax Molybdenum and Rocky Mountain Steel, Xcel’s two largest Colorado customers, have also intervened in the case.

Two days of hearings are scheduled before an commission administrative law judge.

Mark Jaffe: 303-954-1912, mjaffe@denverpost.com or twitter.com/bymarkjaffe

More in Business