Getting your player ready...
As the Spire condominium tower nears completion, the contractor for the project has compiled the quantities of materials used in the downtown building’s construction.
JE Dunn’s key project people, Andrew Gilstrap, project engineer; Dustin Liljehorn, senior project manager; and Eric Snelling, general superintendent, came up with a list of what went into the project. Here are some highlights:
40,739
cubic yards of concrete
1,870 stairs
1.3 million
square feet of drywall
9,000 sprinkler heads
265,433 pounds of granite
107,000 square feet of tile
34,500 square yards of carpet
170,000
square feet of wood flooring
440,542 pounds of duct work
6,656 window panels



