As the Spire condominium tower nears completion, the contractor for the project has compiled the quantities of materials used in the downtown building’s construction.

JE Dunn’s key project people, Andrew Gilstrap, project engineer; Dustin Liljehorn, senior project manager; and Eric Snelling, general superintendent, came up with a list of what went into the project. Here are some highlights:

40,739

cubic yards of concrete

1,870 stairs

1.3 million

square feet of drywall

9,000 sprinkler heads

265,433 pounds of granite

107,000 square feet of tile

34,500 square yards of carpet

170,000

square feet of wood flooring

440,542 pounds of duct work

6,656 window panels