Three months before the Department of Veterans Affairs began building a new hospital in Aurora, an agency contract specialist warned that the project, and one in New Orleans, could face immense cost overruns.

The specialist, Adelino Gorospe, predicted in an e-mail to high-ranking VA construction-management officials that the two medical centers could top their budgets by a combined $500 million.

As it turned out, his estimate was low.

The latest estimate for the — is $1.1 billion above the budget awarded to contractor Kiewit-Turner when construction started more than three years ago.

Gorospe’s warning was one of at least four by various people, including one as early as October 2010, that VA officials received before construction began on a hospital they expected to be “second to none.”

His e-mail, sent Sept. 1, 2011, warned 23 senior agency executives and contracting officials that the VA could be making a huge mistake on the contracts. The recipients included contract supervisor Chris Kyrgos and Glenn Haggstrom, the agency’s construction chief.

“I think we need a reality check!” Gorospe wrote. “I must beg you once again that we rethink our strategies in New Orleans and Denver.”

Already, talk of agency cost savings had turned into an estimated $30 million over budget — “a meaningless or at best a very low estimate, if you ask me,” he wrote.

“Without a change in strategy, my estimate would be around half a billion dollars in total cost overrun: $500 million! That’s how risky this type of contract is,” he added. “Where in this economy are you going to find the money?”

Eight months later, Gorospe lost his job.

He said Haggstrom fired him in April 2012, citing disobedience of his supervisor as a pretext. “They actually escorted me out of my office,” he said.

from the VA’s Office of Acquisition, Logistics and Construction with full benefits, one day after investigators questioned him about cost overruns on the Aurora project.

VA representatives in Washington, D.C., did not respond to requests for comment.

New type of contract

Gorospe was complaining about a contracting method the VA hadn’t tried before. Commonly called integrated design and construct, or IDC, it involves getting designers and the contractor to work together from the outset on a smoothly coordinated plan.

In Aurora, however, the hospital design team began work years before the contractor came aboard, construction began with incomplete drawings and conflicts abounded. The contractor, that it never received a design that could be built within the project budget.

The VA received other warnings.

An independent adviser cautioned as early as October 2010 that project costs kept growing as its design proceeded, according to a U.S. Civilian Board of Contract Appeals ruling in December that the VA had breached its contract with Kiewit-Turner.

In February 2011, according to a court document, the agency’s own IDC consultant warned that the scope, quality and cost of the project could creep with this type of contract, and the original cost estimate can get lost “without constant owner vigilance.”

And in September 2011 — the same month Gorospe sounded his $500 million alarm — an Army Corps of Engineers review commissioned by the VA found that the design work completed before the builder brought its cranes had diminished prospects for an integrated approach.

“The current methodology appears to be counterintuitive to the government’s ability to achieve best value,” the Army Corps concluded.

This week the established by Congress in the wake of a hospital wait-time scandal to come up with an estimated $830 million to finish the hospital in Aurora. Rep. Mike Coffman, R-Aurora, has instead until the hospital opens.

From its beginnings, the vision of a gleaming new medical campus for Rocky Mountain-region veterans featured what critics call extravagant design touches.

According to a detailed summary written in 2009 by the joint venture design team of Skidmore, Owings & Merrill, Cator, Ruma & Associates, S.A. Miro and H+L Architects, the VA medical center itself required that the “quality of care will be second to none and non-negotiable” and that the “physical facility will stand up to any comparison to any other medical center.”

The VA wanted a “linear model” for its hospital, treatment centers and clinics. The design team provided a glass-walled “Main Street” concourse with an arched roof — 170 feet high and more than 1,200 feet long — with Rocky Mountain views.

“Artifacts that convey the veterans’ service experience will also be displayed throughout Main Street,” the design team wrote.

Over the contractor’s objections, the west side of the concourse also featured a zigzag wall on the west side, adding to the price of a lobby already costing more than $100 million.

“Humongous lobby”

In the Kiewit-Turner lawsuit, longtime company executive Mike Colpack called it a “humongous lobby,” possibly the largest in the world “for health care or a building facility.”

James Chang, a VA engineer, testified that the parking garages for the new hospital were designed to cost twice as much as those at Children’s Hospital Colorado next door, and the lobby was another example of “gold-plating” the design.

The layout required 43 elevators to serve hospital facilities built east and west of the glass spine, including parking garages for patients and workers on a 14-building campus.

Indoors, “a planted wall may be integrated into an encased glass terrarium,” the design team suggested, “assisting in controlling internal climatic conditions and improving internal air quality.”

Outdoors, the plan called for gardens for children and patients, cafe seating and an elaborate landscaping design displaying plants found at Colorado’s changing elevations. Plains trees such as cottonwood and willow would grace the perimeter. Foothills pines would grow in the middle. High-altitude trees such as aspen and bristlecone pine would be planted closest to the hospital and above-timberline plants on its rooftops.

“By juxtaposing the building fingers and courtyards, the landscape appears to pass through the building at its spine,” the design team wrote. “This integration of space and form means the medical center sits within the landscape as opposed to resting on it.”

Andy Boian, a spokesman for the design team, said the zigzag wall will diffuse sunlight and reduce solar heat gain, and the landscaping plan meets the allotted budget.

He denied that designers and architects drove up project costs. “We have fulfilled our contractual obligation to the VA on time and on budget,” he said.

E-mails obtained by The Denver Post show Gorospe had been cautioning against integrated design and construct contracts since March 2010, when he wrote, “IDC is a high-risk contract type.”

He put his fears in plain terms. “When you are buying a car, will you, the customer, sign the contract before you negotiate and agree on the final price?” he asked. “This ‘sign contract now-negotiate later’ plan with this IDC is what makes this contract type extremely risky.”

Renee Tietjen, a senior architect with the VA, disputed Gorospe’s warnings. Other federal and state agencies and the private sector used this contracting method successfully “as a way to avoid conflicts and lower risk in construction,” she wrote.

“It is possibly true that VA may not be currently structured or have the right personnel to do this type of procurement as successfully as we would like,” she acknowledged. She suggested that could be fixed by hiring qualified contracting officers or taking “the time to train and mentor people properly.”

Costs spiraled

A year after the VA began building its Aurora hospital campus, an agency letter warned that costs were spiraling out of control already.

Thaddeus Willoughby, a senior officer in the construction branch, wrote to the project’s architectural group that its current design had busted the budget by an estimated $199 million.

He directed them to redesign the project “within funding limitations as required by the contract.”

That never happened.

Instead, high-stakes finger-pointing followed.

In its lawsuit, Kiewit-Turner argued it had been forced to begin work with an incomplete set of drawings — the exact risk Gorospe had pointed out — and the opportunities to cut costs kept dwindling with every month of building construction.

The VA argued that Kiewit-Turner willingly signed a $604 million contract and agreed to work with the designers, and the government was not responsible for changing economic conditions that had raised subcontractor bids.

Kiewit-Turner prevailed, and construction on the 182-bed facility halted in December until the VA came up with enough money to keep the project alive.

Gorospe’s dire prediction also proved correct on the New Orleans project. The U.S. Government Accountability Office reported to Congress this year that it may cost $410 million more than the VA originally estimated.

Denver Post staff writer Mark K. Matthews contributed to this report.